Bauvorbescheid (preliminary building decision): The Authority's Answer Before You Buy the Land

A Bauvorbescheid is the building authority's written decision on individual questions about a future project, valid for three years in Baden-Württemberg and North Rhine-Westphalia and four in Bavaria. Available before a permit application is filed and passing to a buyer of the plot, it removes the main planning risk — whether a store of the required size is admissible — before money goes into the land or the project.

What it is

Before applying for a permit, the party commissioning the works may put individual questions to the authority and obtain a decision on them (§ 57(1) LBO BW; Art. 71 BayBO; § 77(1) BauO NRW). Such questions might be whether a food store of a given size is admissible on the plot, where the building may stand and whether the access is adequate. The decision attaches to the project and applies to successors in title (§ 57(2), § 58(2) LBO BW; Art. 54(2) sentence 3 BayBO; § 58(4), § 77(1) BauO NRW). But it answers only the questions asked: a "yes" under planning law settles neither fire safety nor parking.
The procedure is simpler than a full application. In North Rhine-Westphalia the authority must decide within six weeks of receiving the complete documents. Questions limited to the type of use, the building pattern and the buildable part of the plot do not even require a designer entitled to sign building documents (§ 74(2), § 77(2) BauO NRW).
Exhibit 1. In three states a preliminary decision is valid for three to four years
State
Valid for
Each extension
Baden-Württemberg (§ 57(1), (2), § 62(2) LBO BW)
3 years
up to 3 years
Bavaria (Art. 71 BayBO)
4 years
up to 4 years
North Rhine-Westphalia (§ 77(1) BauO NRW)
3 years
up to 1 year

Why it matters to investors

When buying a plot or a store under construction (see Part 6 of the series German Prime Retail), an investor can make a preliminary decision a condition of the contract and pay only once the main question is settled. The decision also shows where the limit of what is admissible lies. In Cologne, a discounter with about 699 m² of sales area, below the large-scale threshold, was refused one. The appeal court found that it would harm a nearby local centre with a 640 m² supermarket and a 570 m² discounter. The Federal Administrative Court upheld that finding (BVerwG, judgment of 17 December 2009, 4 C 2.08).
The decision is an asset with an expiry date. Once it lapses, the question must be put again, possibly under different rules, so check that a decision obtained by the seller is still valid.

What to check

• The exact wording of the questions and answers: what is decided and what remains open.
• The date of issue, the validity period under state law and any applications to extend it.
• Whether the project being bought matches the decision's parameters: sales area, range of goods, position of the building.
• Neighbours' objections to the decision and how far they have progressed.
Sources: BauGB § 34; LBO BW §§ 57, 58, 62; BayBO Arts 54, 71; BauO NRW §§ 58, 74, 77; BVerwG, judgment of 17 December 2009, 4 C 2.08; Gordon Real Estate Group, "German Prime Retail", Part 6. Legal position as of 10 October 2026.
Photo: Lucas Kepner / Unsplash
This entry is general information and not legal or tax advice.