Baugenehmigung (building permit): The Document That Defines the Asset

A Baugenehmigung is the building authority's decision that a building and its use comply with public law. For a supermarket, the permit and the lease together define the asset: the permitted sales area, use and parking are what the investor actually owns (see Part 3 of the series German Prime Retail).

What it is

The state building codes govern the procedure. A permit is granted if the project does not conflict with the public-law provisions the authority must examine (§ 58(1) LBO BW; Art. 68(1) BayBO; § 74(1) BauO NRW). It attaches to the project, not to the owner, and takes effect for and against the successors of the party commissioning the works (§ 58(2) LBO BW; Art. 54(2) sentence 3 BayBO; § 58(4) BauO NRW). It is also granted without prejudice to the private rights of third parties, so it does not settle a dispute with a neighbour over easements (§ 58(3) LBO BW; Art. 68(5) BayBO).
For a large store the core of the review is planning law: conformity with the development plan or with the surrounding built-up area (§§ 30, 34 BauGB). In some cases the municipality must consent, and its consent is deemed given if it does not refuse within two months (§ 36 BauGB). A neighbour's objection or lawsuit does not suspend the permit (§ 212a(1) BauGB): building may go ahead, but the permit becomes final only once it can no longer be challenged. A permit lapses if construction does not start in time; the deadlines differ by state, and in Bavaria a challenge suspends them (Art. 69(1) BayBO).
Exhibit 1. In three states a permit lapses if construction has not started within 3–4 years
State
Permit lapses if work has not started within
…or has been interrupted for
Each extension
Baden-Württemberg (§ 62 LBO BW)
3 years
1 year
up to 3 years
Bavaria (Art. 69 BayBO)
4 years
4 years
up to 4 years
North Rhine-Westphalia (§ 75 BauO NRW)
3 years
more than 1 year
up to 1 year

Why it matters to investors

An investor who buys a store under construction pays for a building that does not yet exist, so the permit must be granted and final, and work must start in time (Part 6). A permit granted before the municipality imposed a development freeze (Veränderungssperre) to secure a new plan is not affected by it (§ 14(3) BauGB).
For a store already trading the question is different: do the building and its operation match what was permitted — sales area, use, parking (Part 7)? Grandfathering (Bestandsschutz) covers only the store as approved, so every unpermitted alteration is a risk on sale and at the next extension.

What to check

• The permit with all approved drawings, conditions and later amendments, and whether it has become final.
• The permitted sales area, range of goods, use and number of parking spaces against the store as it trades.
• For a store under construction, the date of grant, the start of work and the permit's validity under state law.
• Neighbours' objections and lawsuits against the permit, and the municipality's consent where it was required.
Sources: BauGB §§ 14, 30, 34, 36, 212a; LBO BW §§ 58, 62 (version of 16 March 2026); BayBO Arts 54, 68, 69 (version in force from 1 May 2026); BauO NRW §§ 58, 74, 75 (version in force from 1 September 2026); Gordon Real Estate Group, "German Prime Retail", Parts 3, 6 and 7. Legal position as of 10 October 2026.
Photo: Lucas Kepner / Unsplash
This entry is general information and not legal or tax advice.